Hammer crusher initial installation test process

  1. Select the topography according to the source of raw materials before installation.
    2, the location of electrical equipment is convenient to use.
  2. Check for proper lubricant in the bearing.
  3. The motor should be installed in the opposite direction to the feed port.
  4. After the installation is completed, it is necessary to carefully check and confirm that all the components and all the connections are assembled correctly, and no tools or instruments are left in the crushing chamber before the test can be carried out.
  5. Check whether the bolts of each part are tightened, whether the safety guard is installed properly, and whether the chain transmission and the motor are normal.
  6. When testing the vehicle, first use the human power to drive the rotor for 2-3 weeks. Before the operation is flexible, it is determined that there is no resistance before driving. After driving, it is necessary to carry out a one-hour no-load test run to see if there is any problem.
  7. The load test should be evenly fed. The feed rate should be gradually increased from the number to the rated quantity. The spindle temperature should be below 60 °C.
  8. After the test run is completed, the feed should be stopped first. When there is no material in the feeder, stop the feeder; the materials in the machine cavity can be stopped before being processed.